Update on Chicago-Halsted Viaduct and Bridge Project from Alderman Burnett

Dear Neighbor,
We have an update on the Chicago–Halsted viaduct and bridge project.
What’s open now
As of Friday, November 13, Halsted Street is open between Superior Street and Erie Street. If you live or work just southwest of Chicago and Halsted, you should find it easier to get in and out of the area. CDOT will be watching traffic conditions as drivers adjust.
What’s still closed
Halsted at Chicago Avenue and to the north remains closed. Please continue following the posted detour signs. CDOT is aiming to reopen the rest of Halsted around January 1 and will share another update before then. We’ll pass it along as soon as we hear.
What you’ll see in the coming weeks
Crews are building the new road deck in the Chicago–Halsted intersection and assembling the new Chicago Avenue river bridge on land, which will then be moved into place over the river. Work will also begin on a new water main along Chicago Avenue and new pavement on Halsted south of Chicago, so expect continued construction activity in the area.
What’s already done
The old viaduct and the old Chicago Avenue bridge have been removed, and the new viaduct’s foundation and steel frame are in place. Chicago Avenue west of Halsted has new pavement, drainage, and sidewalks.
When it’s finished
The full project is expected to wrap up this spring. When it does, the area will have a new bridge over the river, a rebuilt viaduct, a riverwalk connection, protected bike lanes, dedicated CTA bus lanes, and better lighting and traffic signals.
Also nearby
Separate from this project, Grand Avenue near the Bally’s site is back to two lanes in each direction, but you may run into occasional lane closures through the end of the year.
We know this construction has been hard on residents and businesses, and we appreciate your patience.
Sincerely,
Alderman Walter Redmond Burnett
27th Ward