Notice of Department of Water Management Work – Near North

The Department of Water Management (DWM) is currently working on the following projects in the 2nd Ward:

Project No: 1301291
Near North

The Department of Water Management will be working on Chestnut Street between Orleans and Wells. ADA-compliant sidewalk ramps will be repaired or installed where needed, along with repair of damaged parkway and sidewalk. The final restoration of the street will include milling the surface, placing new asphalt, and painting the street markings. Over the next few weeks additional work will begin to restore the street temporarily with concrete until complete restoration of the street with asphalt can be done. The concrete work is expected to be completed by Mid-October 2018.

Source:  Alderman Hopkin’s Newsletter 10/9/18